Navigation: Account Delinquency screen > Comments tab > Comments field group >
Loss Mitigation Start/End
Entry: User, date
F/M: Yes
Mnemonic: QALSDT, QALEDT
Screen: Account Delinquency; Bankruptcy; Foreclosure & Repossession & Judgment; Collection Queues, Detail & Queue Processing tab, Comments tab
Field Group: Comments
Enter the date that the activity in the Loss Mitigation field began in the Loss Mitigation Start field and the date it was completed in the Loss Mitigation End field. The dates will be displayed in the Comments list view at the bottom of the screen. In addition, the dates will also remain in the fields, providing you with the ability to access them from GOLDWriter.
Note: An error provider () will be displayed if you only have a loss mitigation start date or end date or if the start date is later than the end date.
Note: A warning provider () will be displayed if a repayment plan is found but the loss mitigation dates aren't set.